Wednesday, December 30, 2009

Secant Pile Walls and Tagent Pile Wall





Secant pile walls are formed by constructing intersecting reinforced concrete piles. The piles are reinforced with either steel rebar or with steel beams and are constructed by either drilling under mud or augering. Primary piles are installed first with secondary piles constructed in between primary piles once the latter gain sufficient strength. Pile overlap is typically in the order of 3 inches (8 cm). In a tangent pile wall, there is no pile overlap as the piles are constructed flush to each other. The main advantages of secant or tangent pile walls are:
1. Increased construction alignment flexibility.
2. Increased wall stiffness compared to sheet piles.
3. Can be installed in difficult ground (cobbles/boulders).
4. Less noisy construction.
The main disadvantages of secant pile walls are:
1. Verticality tolerances may be hard to achieve for deep piles.
2. Total waterproofing is very difficult to obtain in joints.
3. Increased cost compared to sheet pile walls.

Secant pile wall design when steel beams are used involves the use of weaker than normal concrete. The pile that is lagging the wall between two main beams has to be examined for shear and compression arching.






Secant pile walls can be used for temporary support of deep excavations or to form permanent earth retention systems. They can also serve the dual function of excavation support during construction and as part of the permanent foundation system. Since secant pile installation creates minimal disturbance, this technique is suited for dense, urban environments. Walls are constructed by the sequenced construction of overlapping, reinforced concrete piles installed in a top-down process by either drilling or augering methods.  Although more costly than sheeted excavation support, this system offers greater alignment flexibility and increased wall stiffness and can be installed through bouldery or cobbly soils.






Secant pile wall construction is the most economical method of creating an effective water control barrier for dam remediation. Drilling techniques are used to construct overlapping concrete elements through rock, extending below the water seepage elevation. Sequenced drilling and concreting of the individual elements that make up the finished barrier allows the concrete to cure, ensuring a tight seal between elements for complete water cut off. Secant Pile Walls can be constructed to depths of 120 ft.


More Information on Basement & Slope Retention
Contiguous pile wall - typical diameters and spacing


Diameter
mm
Spacing
mm

350
450
600
750


400
600
750
900

Secondary hard/soft secant pile wall - typical diameters and spacing


Diameter
mm
Spacing
mm
Primary
Secondary


450
600
750


450
600
750

600
900
1000
 Note:  The gap between the primary or structural piles should not exceed 40% of the diameter of the soft piles


Typical applications of embedded retaining walls
(ICE Specification for Piling and Embedded Retaining Walls)


Wall Type
Typical height range
Groundwater control
Typical vertically
Cantilever
Propped
Temp.
Perm.
Sheet pile wall
To 5m
4 - 15m
Yes
No
1:75
Combination wall
To 10m
5 - 20m
Yes
No
n/a
King post
To 4m
4 - 20m
No
No
n/a
Contiguous
To 5m
4 - 20m
No
No
1:75
Hard/soft secant
To 5m
4 - 20m1
Yes2
No
1:75
Hard/hard secant
To 6m
4 - 25m
Yes
Yes
1:200
Diaphragm wall
To 8m
5 - 30m
Yes
Yes
1:75

Notes:
1.  The depth to which hard/soft pile walls can provide water resistance is restricted by 
     the construction tolerances of the boring rig and the groundwater pressure to be
     resisted.  This type of wall is most commonly used to resist groundwater flow to
     maximum depths of approximately 6m.

2.  The long term resistance of the soft elements of hard/soft secant pile walls to
     groundwater flow has not been proven and will vary according to the soft mix design. 
     It is recommended that long term water resistance is provided for by additional works
     such as reinforced concrete lining walls which transfer the groundwater load into the
     hard elements.



Tangent Pile Wall



Tangent pile walls are a variation of secant pile walls and soldier pile walls. However, tangent pile walls are constructed with no overlap and ideally one pile touches the other. Compared to secant pile walls, tangent pile walls offer the following advantages:
1. Increased construction alignment flexibility.
2. Easier and quicker construction.




The main disadvantages of tangent pile walls are:
1. They are can not be used in high groundwater tables without dewatering.
2. Each pile is independent from adjacent piles




No comments:

Post a Comment

Sebarkan ke Facebook

Google Followers

Seputar Teknologi Konstruksi

TOP RANK

  • Inhibitor - *Inhibitor* merupakan zat yang menghambat atau menurunkan laju reaksi kimia. Sifat inhibitor berlawanan dengan katalis, yang mempercepat laju reaksi. *Inh...
    12 years ago